Aletheia Public Understanding Series · Aviation, technology & oversight
Research snapshot: Friday evening, November 13, 2026 This is a living investigation; figures and technical findings may change.
What happened, what was already working, where the money went, and what we still do not know.
On November 13, 2026, a telecommunications disruption led the FAA to temporarily halt most departures nationwide. The halt was lifted later that day, but a definitive technical root-cause report had not been made public as of this review. A public safety action, an equipment defect and a decision to fund modernization are different things. This page examines each separately, without assigning unproven blame.

1. What happened on November 13?
The FAA issued a rare nationwide ground stop after communications problems were reported in its regional air traffic control network. Departing aircraft were largely held on the ground; many already-airborne flights continued to land or were diverted. Some international flights and flights within Alaska and Hawaii were handled differently. The FAA later authorized departures to resume, but cancellations and delays continued. Associated Press, November 13.
Officials described the issue as a telecommunications outage and discussed overloaded equipment. Those are reported explanations, not yet a completed forensic finding. Officials reported no indication of a cyberattack at the time. The FAA’s newer AI-based planning system and a separate Microsoft outage were also discussed publicly, but no verified causal link was established in the evidence reviewed. Associated Press reporting.
Two different scales: A nationwide ground-stop order tells us the scope of the safety response. It does not by itself tell us exactly how many individual routers, radios, radars, or control centers physically failed. Determining the equipment failure’s footprint requires technical logs and a final incident report.
2. The system was not frozen in the 1980s
From hand signals to computerized control: these historical images show how air traffic technology evolved over generations.


Airplanes and air traffic control have used computers and sophisticated automation for decades. Flight-management computers aboard aircraft are distinct from ground systems that track aircraft and coordinate safe separation. Both must communicate reliably, and both have undergone repeated upgrades.
In April 2015, the FAA reported completion of En Route Automation Modernization (ERAM), replacing a much older computer system at all 20 high-altitude control centers in the continental United States. In 2025, the FAA also reported additional NextGen improvements, including continuous data-communications service at those 20 centers. Sources: FAA 2015 ERAM announcement and FAA NextGen accomplishments.
At the same time, the independent Government Accountability Office (GAO) reported in September 2024 that, in an FAA assessment of 138 air traffic control systems, 51 were classified as unsustainable, 54 as potentially unsustainable, and 33 as having no identified sustainment problems. Reasons included spare-parts shortages, insufficient support, and aging functions—not simply the year an item was built.
Critically, 64 modernization investments were already underway, addressing 90 of the 105 systems classified as unsustainable or potentially unsustainable. So two statements are supported at once: real system weaknesses existed, and previous generations had been actively maintaining and improving the network. GAO-24-107001, September 2024.
■ 51 unsustainable (37%) ■ 54 potentially unsustainable (39%) ■ 33 without sustainment issues (24%)
This is the FAA’s sustainability classification, not a count of systems that had stopped functioning.
3. Newark, 2025: an identifiable problem and a completed repair

Communications and radar-data interruptions affected the Newark approach-control operation in spring 2025. On May 8, 2025, the Department of Transportation announced a national modernization plan covering telecommunications, surveillance, automation, and facilities. Original FAA announcement.
On July 3, 2025, the FAA announced that it had switched Newark-related operations onto a new fiber-optic communications network between New York and the Philadelphia terminal approach-control facility. Officials described two physically separate communications paths and testing conducted during June. This was a specific, reported improvement to a specific vulnerability. FAA completion announcement.
That completed work should not be confused with the much larger national modernization program. A later failure elsewhere in the regional network would not, by itself, prove the July upgrade was fraudulent or ineffective; a technical investigation must identify which components failed and whether they were part of that project.
4. The money: approved funding is not the same as a request
| When | Amount | What it means |
|---|---|---|
| July 2025 | $12.5B | Congress appropriated funds for specific FAA systems, facilities and safety work, available over multiple years. |
| Nov. 13, 2026 (morning) | $30.1B | Administration requested additional appropriations; a request is not money spent. |
| Nov. 13, 2026 (evening) | About $50B | Officials called for roughly $50B in funding after the shutdown. Public reporting does not establish this as an additional enacted appropriation on top of the morning request. |
The 2025 law specifically included $4.75B for telecommunications and systems upgrades, $3B for radar replacement, $1.9B for an en route control center, and other named categories. It also requires FAA expenditure reports to Congress every 90 days after an initial report. Public Law 119-21, section 40003.
The November 13 morning request proposed $10.1B for air traffic control modernization, $2B for control towers, and $18B for airport projects, including terminals. These categories extend well beyond fixing a single telecommunications failure. Later Friday, Reuters reported a broader $50B funding call. Readers should not add all these announcements together as if they were separate approved checks. Reuters, November 13 funding coverage.
Financial vocabulary: an appropriation makes budget authority available; an obligation is a legal commitment such as a contract award; a payment is money actually disbursed; and a contract ceiling is a maximum, not proof that the maximum has been paid.
5. What were the contractors hired to do?
| Organization | Assigned role | What is confirmed |
|---|---|---|
| Peraton | Prime systems integrator: coordinate work across 13 Phase 1 modernization programs and other contractors. | $1.5B contract ceiling; GAO reported about $876M negotiated price. Neither figure is proof of cash paid. |
| RTX (Raytheon) | Supply replacement surveillance radars. | FAA announced a radar award January 5, 2026. Delivery and acceptance must be verified separately. |
| Indra | Supply replacement surveillance radars. | FAA announced a separate radar award January 5, 2026. This is not the same as paying to resolve Newark’s single outage. |
The FAA stated RTX and Indra would help replace up to 612 radars by June 2028 and reduce the number of radar configurations in the system. These companies were already participants in aviation or related communications technology before these awards; the award announcements do not establish that they caused the November 13 disruption. Sources: FAA Peraton award, FAA radar awards, and GAO September 2026 audit.
GAO also reported that radar-installation oversight was shifted from Peraton to the radar vendors during negotiations, and that officials said this reduced the integrator’s negotiated price. This was a change in allocation of responsibility, not evidence by itself that any work was completed or any money misused. GAO-26-107992.
6. What had actually been completed?
The FAA’s Modern Skies dashboard, marked October 15, 2026, reported 3,508 of 5,170 telecommunications connections replaced and 15 of 612 radar systems deployed. These are agency-reported progress counts, not independent acceptance certificates. The dashboard may be revised. FAA deployment dashboard.
GAO’s September 2026 audit reported that, as of March 2026, FAA had obligated about $1.8B of roughly $9B then allocated to the first phase’s system programs. Obligations are not the same as completed work or paid invoices. Auditors also reported that FAA had 11,389 separate project schedules without a fully integrated master schedule, and lacked a comprehensive, supported lifecycle-cost estimate. GAO-26-107992.
Balanced finding: Completed installations are documented. Unfinished work, cost uncertainty, and coordination risks are also documented. Both belong in the same public accounting.
7. The engineering questions: isolation, redundancy, and human responsibility
A well-managed technical change should minimize the area exposed to failure. A backup network should be meaningfully independent, and testing should include failover, rollback and restoration—not just whether new software starts successfully. These are sound engineering principles, but they are questions to test against the FAA’s actual architecture, not evidence that a particular contractor violated them.
A simplified information path
Aircraft and surveillance sensors → communication links → control-center systems → controllers and flight crews
Illustration only. Real FAA systems have many parallel routes, backups and procedures; this is not a diagram of the November 13 failure.
A shutdown that affects flights across the country can be a nationwide precautionary order in response to a more limited equipment problem. To identify the actual failure’s spread, an investigation must compare affected sites, common network services, change logs, redundant paths, and restoration records.
- First failure: Which component failed first, and at what exact time?
- Shared dependencies: Which facilities used the same routers, circuit providers, update services or data exchanges?
- Isolation: Why was the affected service not contained, or was a wider halt the correct safety response?
- Testing: Were primary and backup systems tested under realistic failure conditions?
- Approval: Who signed off on system changes, and what acceptance records exist?
- Results: Which promised projects are operational, and what measurable reduction in disruptions followed?
- Money: What did Congress appropriate, which contracts were obligated, what was paid, and which deliverables were accepted?
8. The historical perspective
Infrastructure is built across generations. The same aviation system can contain long-lived radios, newer digital systems, decades of operator knowledge and recently introduced planning software. Historical continuity matters: a change in leadership does not erase previous work, and the age of a component alone is not proof of neglect.
Our focus is on the movement of information and responsibility—what people knew, what equipment they relied on, who could approve changes, how safely systems were maintained, and how the public explanation compares with the records. An official statement, an audit finding, a contractor’s promise and a completed field test are not interchangeable kinds of evidence.
What is not established as of this snapshot: that the November 13 interruption was deliberately caused; that a new AI tool caused it; that particular contractors were responsible; or that the full proposed spending is already approved or spent. These possibilities must not be stated as facts without records.
9. Primary records and reporting
These links allow readers to check the statements above and see the source material in context.
- GAO September 2024 — Air Traffic Control: FAA Actions Are Urgently Needed to Modernize Aging Systems (2023 inventory, earlier work).
- FAA April 2015 — ERAM completion and FAA NextGen accomplishments (historical modernization).
- FAA May 8, 2025 — New air traffic control system plan and FAA July 3, 2025 — Newark communications upgrade.
- Public Law 119-21, section 40003 (2025 appropriation and quarterly expenditure reporting).
- FAA December 2025 — Peraton integrator and FAA January 2026 — RTX and Indra radar awards.
- GAO September 14, 2026 — cost and scheduling audit (integrator pricing, obligations, project coordination).
- FAA Modern Skies dashboard (reported installations; snapshot dated October 15, 2026).
- Associated Press — November 13 ground stop and reopening and Reuters — November 13 funding requests (breaking developments; subject to updates).
Editorial method: Aletheia separates documented events, officials’ explanations, expert/auditor findings, and unanswered questions. This page does not endorse a political party or make findings about anyone’s undisclosed intentions. The operational incident report, financial expenditure records and acceptance-test documentation are the next records needed. Prepared November 13, 2026; not a final incident investigation.